Earliest finish time ( EF ) is the earliest time by which a specific activity can be completed, calculated Group of answer choices by subtracting

Earliest finish time (EF) is the earliest time by which a specific activity can be completed, calculated
Group of answer choices
by subtracting the activitys estimated duration from the earliest finish time of the activity's predecessor: EF = EF predecessor - Estimated Duration.
by subtracting the activitys estimated duration to the activitys earliest start time: EF = ES - Estimated Duration
by adding the activitys estimated duration to the earliest start time of the activity's succeeding activity: EF = ES succeeding activity + Estimated Duration.
by adding the activitys estimated duration to the activitys earliest start time: EF = ES + Estimated Duration.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Transport Operations

Authors: Allen Stuart

2nd Edition

978-0470115398, 0470115394

More Books

Students also viewed these General Management questions