Early in 2018, Desert, Co. finalized plans to expand operations. The first stage was completed on January 19th with the purchase of a tract of
Early in 2018, Desert, Co. finalized plans to expand operations. The first stage was completed on January 19th with the purchase of a tract of land to be used as the location for their new office complex. The land and existing building were purchased for $850,000, paying cash. Title search, title insurance, back property taxes and other closing costs totaling $20,000 were paid at closing.
During February, the old building was demolished at a cost of $70,000, and an additional $50,000 was paid to clear and grade the land. Salvaged materials from the demolished building were sold for proceeds of $20,000. Construction of the new office complex began on March 1 and was completed on November 30, 2018. Construction expenditures paid to sub-contractors were made as follows:
March 1 | $ 900,000 |
June 1 | $1,200,000 |
Sept 1 | $1,500,000 |
Nov 1 | $1,800,000 |
Desert borrowed a $2,100,000, 8%, 2-year note on February 1st to help finance construction. Interest will be paid annually. The company's only other outstanding debt during all of 2018 was a $3,000,000, 9%, 10-year note payable.
In December, the company purchased equipment and furniture for a lump-sum price of $500,000. The fair values of the equipment and furniture were $455,000 and $245,000, respectively.
Given this information, determine the Original Cost of the Land.
Using the information presented in Question 1 above, determine the Historical Cost of the building after taking into consideration the capitalization of interest.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started