Earned Value Management (EVM3) 33 2 points You are working on a project that is scheduled to be completed in 10 months. The total budget

image text in transcribed
Earned Value Management (EVM3) 33 2 points You are working on a project that is scheduled to be completed in 10 months. The total budget for the project is $10,000. Six months have passed and the schedule indicates What is the Planned Value (PV) for this project at this point in time? that 60% of the work should be completed by now. But your team has only O $10,000 * 60% = $6,000 completed 50% of the project and spent $8,000. $8,000 $ 50% = $4,000 $8,000 * 60% = $4,800 O $10,000 * 50% = $5,000 34 2 points What is the Earned Value (EV) for this project at this point in time? $10,000 * 50% = $5,000 OOO $8,000 * 50% = $4,000 $10,000 * 60% = $6,000 O $8,000 * 60% = $4,800

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quantitative Methods For Business

Authors: David Anderson, Dennis Sweeney, Thomas Williams, Jeffrey Cam

11th Edition

978-0324651812, 324651813, 978-0324651751

More Books

Students also viewed these General Management questions

Question

What is loss of bone density and strength as ?

Answered: 1 week ago

Question

The paleolithic age human life, short write up ?

Answered: 1 week ago