Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Earned-value analysis. A project budget calls for the following expenditures: Task Date Budgeted Amount Build forms April 1 $10,000 April 1 $50,000 Pour foundation May
Earned-value analysis. A project budget calls for the following expenditures: Task Date Budgeted Amount Build forms April 1 $10,000 April 1 $50,000 Pour foundation May 1 $100,000 May 1 $30,000 Frame walls June 1 $30,000 Remaining tasks July 1 and beyond $500,000 5. SV as of May 1. 6. Actual cost as of May 1 is $160,000. Calculate the cost variance (CV) as of May 1. 7. Schedule performance index (SPI) 8. Cost performance index (CPI) 9. Estimate to complete (ETC), assuming that the previous cost variances will not affect future costs 10. Estimate at completion (EAC)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started