Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Earned-value analysis. A project budget calls for the following expenditures: Task Date Budgeted Amount Build forms April 1 $10,000 Pour foundation April 1 $50,000 May
Earned-value analysis. A project budget calls for the following expenditures:
Task | Date | Budgeted Amount |
Build forms | April 1 | $10,000 |
Pour foundation | April 1 | $50,000 |
May 1 | $100,000 | |
Frame walls | May 1 | $30,000 |
June 1 | $30,000 | |
Remaining tasks | July 1 and beyond | $500,000 |
Define each term in your own words, calculate these values for the above project, and show your work:
- SV as of May 1.
- Actual cost as of May 1 is $160,000. Calculate the cost variance (CV) as of May 1.
- Schedule performance index (SPI)
- Cost performance index (CPI)
- Estimate to complete (ETC), assuming that the previous cost variances will not affect future costs
- Estimate at completion (EAC)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started