ect manager has to pay penalty 0:16:08er day. Indirect project .costs = $250 per day Project Activity and Cost Data Immediate Crash Crash Normal
ect manager has to pay penalty 0:16:08er day. Indirect project .costs = $250 per day Project Activity and Cost Data Immediate Crash Crash Normal Normal Activity edecessor(s) Cost Time Cost Time ($)(days) ($) (days) 1200 4 1000 LO A 2000 3 800 LO B A, B 900 1 600 2 C B 2000 2 1500 3 D C, D 1200 3 900 LO E E 1400 1 1300 2 F E 900 3 900 3 G G 900 3 500 LO 5 H A ?Which activity will be crashed first activity B .a O activity D .b O activity E .CO activity H .d O