End of Week Number 1 2 3 4 5 6 7 PV $ 60,000 $ 25,000 $ 15,000 $ - $ 30,000 $ 30,000 $
End of Week Number | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
PV | $ 60,000 | $ 25,000 | $ 15,000 | $ - | $ 30,000 | $ 30,000 | $ 30,000 |
EV | $ 60,000 | $ - | $ 25,000 | $ 15,000 | $ 30,000 | $ 30,000 | $ 30,000 |
AC | $ 62,000 | $ - | $ 26,000 | $ 15,000 | $ 32,000 | $ 33,000 | $ 30,000 |
1. What is the planned value (PV) at the END OF WEEK 7? |
2. What is the earned value (EV) at the END OF WEEK 7? |
3. What is the actual cost (AC) at the end of WEEK 7? |
4. What is the cost variance (CV) at the end of WEEK 7? |
5. What is the schedule variance (SV) at the end of WEEK 7? |
6. What is the cost performance index (CPI) at the end of WEEK 7? |
7. What is the schedule performance index (SPI) at the end of WEEK 7? |
8. At the end of WEEK 7, how is this project performing? Use CPI nd SPI to justify your conclusion. |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started