Question

...
1 Approved Answer

Engineering economics aid. A project is required to be crash-completed in only 14 weeks instead of normal completion time. You can accelerate a task by

Engineering economics aid.

image text in transcribed
A project is required to be crash-completed in only 14 weeks instead of normal completion time. You can accelerate a task by completing it somewhere in between the fastest crash completion time and normal completion time. It you do that, please use linear interpolation to find the cost per week for duration in between normal and fastest crash completion. The Work Breakdown Structure of the project is tabulated as follows: Normal completion Fastest Crash Completion Work package Time Cost Duration Predecessor (weeks) ($Iweek) (weeks) Cost ($lweek) 20,000 90,000 10,000 22,000 10,000 20,000 5,000 9,000 [a] Create the Activity on Node (AON) network representation of this project. [b] Calculate the slack for each work package. [c] identify the critical path under normal completion durations. [d] if the project is to be crash-completed in only 14 weeks. Create an optimal crash schedule for each work package in the project

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Corporate Finance

Authors: Stephen Ross, Randolph Westerfield, Jeffrey Jaffe

10th edition

978-0077861759

Students also viewed these Economics questions

Question

Differentiate 3sin(9x+2x)

Answered: 1 week ago