Question
Entity A commenced a contract to build a non-current asset for Entity B in the year ended 30 September 2018. The contract price was agreed
Entity A commenced a contract to build a non-current asset for Entity B in the year ended 30 September 2018. The contract price was agreed at $1,500 and the total expected costs of the contract have been confirmed as $800. Entity A will satisfy the performance obligation over time.
The following figures were correctly recognised in the Statement of Profit or Loss for the year ended 30 September 2018:
- Revenue $450
- Cost of Sales $240
- Profit $210
The following figures are also relevant in relation to this contract:
- 2018 2019
- Costs incurred to date $325 $575
- Work certified to date $450 $1,050
Entity A recognises progress on a work certified basis.
REQUIRED:
Measure the contract revenue and contract cost for Entity A in its Statement of Profit or Loss for the year ended 30 September 2019.
ANSWER:
Contract revenue = $Blank 1
Contract cost = $Blank 2
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started