Entry for Jobs Completed; Cost of Unfinished Jobs The following account appears in the ledger prior to recognizing the jobs completed in January: Work in
Entry for Jobs Completed; Cost of Unfinished Jobs
The following account appears in the ledger prior to recognizing the jobs completed in January:
Work in Process | ||
Balance, January 1 | $18,300 | |
Direct materials | 148,780 | |
Direct labor | 160,490 | |
Factory overhead | 84,360 |
Jobs finished during January are summarized as follows:
Job 210 | $74,150 | Job 224 | $86,510 | |
Job 216 | 45,310 | Job 230 | 156,530 |
a. Journalize the entry to record the jobs completed. If an amount box does not require an entry, leave it blank.
____________ | ( ) | ( ) | |
____________ | ( ) | ( ) |
b. Determine the cost of the unfinished jobs at January 31. ________$
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started