Essential of Software Engineering 4th Edition. Chapter 13 Exercises 13.5 We saw in the EV example shown in Table 13.4 that there is more actual
Essential of Software Engineering 4th Edition. Chapter 13 Exercises 13.5
We saw in the EV example shown in Table 13.4 that there is more actual effort spent than what the BCWP indicates on 4/5/2012 because that calculation only includes the completed tasks. Suppose we invent another term called all actual efforts spent (AAES) to include all the efforts spent as of the status date and then use it to compute a new formula: EV9 = AAES / BAC. a. Discuss your opinion of utilizing EV9 instead of EV. b. Because AAES is just a redefined and expanded BCWP, do you believe the SV and CV figures will be more representative of the true project status if we use AAES in computing SV and CV? Why?
Table 13-4 Earned Value Example Date: 4/5/2012
Work Tasks | Estimated Effort in Pers-days | Actual Effort Spent So Far in Pers-days | Estimated Completion Date | Actual Completion Date |
1 | 10 | 10 | 2/5/2012 | 2/5/2012 |
2 | 15 | 25 | 3/15/2012 | 3/25/2012 |
3 | 30 | 15 | 4/25/2012 | |
4 | 25 | 20 | 5/5/2012 | 4/1/2012 |
5 | 15 | 5 | 5/25/2012 | |
6 | 20 | 15 | 6/10/2012 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started