Question
Estimated or budgeted cost and operating data for three companies for 2013 are given below: Company X Company Y Company Z Units to be produced
Estimated or budgeted cost and operating data for three companies for 2013 are given below:
Company X Company Y Company Z
Units to be produced 10,000 8,000 12,000
Machine- hours 50,000 10,000 6,000
Direct labour- hours 12,000 16,000 36,000
Direct labour cost $48,000 $64,000 $150,000
Factory overhead cost 150,000 40,000 60,000
Predetermined overhead rates are calculated on the following bases in the three companies:
Overhead rate based on
Company X Machine-hours
Company Y Direct labour-hours
Company Z Direct labour cost
Required:
a. Calculate the predetermined overhead rate to be used in each company during 2013.
b. Assume that three jobs are worked on during 2013 in company X. Machine-hours recorded by jobs are: job 23, 21,000 hours; job 29, 16,000 hours; and job 31, 11,000 hours. How much overhead will the company apply to work in process? If actual overhead costs total $149,000 for 2012, will overhead be over- or under-applied? By how much?
c. Of what value is the schedule of cost of goods manufactured and how does it tie into the profit and loss statement. Discuss.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started