Estimates based on the assumption that historical data can be used as a frame of reference for current estimates are: Select one: a . Definitive
Estimates based on the assumption that historical data can be used as a frame of reference for current estimates are:
Select one:
a
Definitive estimates.
b
Ballpark estimates.
c
Feasibility estimates.
d
Comparative estimates.