Every environmental impact statement (EIS) must contain a(n) ___. Multiple select question. descriptions of alternatives to the proposed action exact time line for the project
Every environmental impact statement (EIS) must contain a(n) ___. Multiple select question. descriptions of alternatives to the proposed action exact time line for the project explanation of the purpose and need for the project statement of positive and negative environmental impacts of the proposed activity cost-benefit analysis