EVM Cost and Schedule Variances and Performance Indices Suppose you have a project consisting of three activities. Midway through the project you collect the following
EVM Cost and Schedule Variances and Performance Indices
Suppose you have a project consisting of three activities. Midway through the project you collect the following information:
Activity | PV | EV | AC |
1 | 30 | 40 | 35 |
2 | 20 | 15 | 15 |
3 | 10 | 10 | 15 |
What is the project-level Schedule Variance (SV) and Cost Variance (CV)? What is the project-level Schedule Performance Index (SPI) and Cost Performance Index (CPI)?
Under what conditions would a positive variance and a performance index less than 1.0 occur simultaneously?
Topic 5b: Corrective Action
Describe any performance "thresholds" used by your organization to signal when corrective action is required to get a project back on track. If no "thresholds" are used, describe how your organization determines when to apply corrective action. In this context, use the PMI definition of corrective action - "an intentional activity that realigns the performance of the project work with the project management plan".
Option: If you work in an agile environment, describe when, in the process, corrective action is identified and how the effects of corrective action are assessed.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started