Answered step by step
Verified Expert Solution
Question
1 Approved Answer
EX6-21 (Algo) Given the following information, compute... Given the following information, compute the early, late, and slack times for the project network. ID Task Duration
EX6-21 (Algo) Given the following information, compute... Given the following information, compute the early, late, and slack times for the project network. ID Task Duration Predecessor A B Interview users Define new features 11 7 3D9 E C Order components Build prototype Test Field test 2 9 5 DCC B A Lag 7 11 Lag 8 B What is the ES for Activity D? What is the LF for Activity E? What is the slack for the start of Activity E? What is the slack for the end of Activity E? Lag 3 Lag 8 Additional Lag Lag Relationships 8 Start-start A to B Finish-finish A to B 7 Finish-start C to D Finish-start C to E Finish-finish D to E 833 D What is the slack for the end of Activity B? What is the length of the project? time periods. Lag 3 The CyClon project team has started gathering the information necessary to develop a project network-predecessor activities and activity time in days. The results of their meeting are found in the following table: Activity Description Duration Predecessor A Design 8 B Procure prototype parts 11 C Fabricate parts 6 A D Assemble prototype 6 B, C E Laboratory test B D P Field test 9 G Adjust design 10 F B Order stock components 9 G I Order custom components 10 G J Assemble test production unit 11 H, I K Test unit 1 J L Document results X Part A. Draw the project network. Compute the early, late, and slack times for each activity. What is the ES for Activity D? What is the LF for Activity H? What is the slack for Activity C? What is the slack for Activity H? What is the slack for Activity 1? What is the length of the project? What is the critical path? time periods. Part B. Upon further review the team recognize that they missed three finish-to-start lags. Procure prototype parts will involve only 6 days of work but it will take 5 days for the parts to be delivered. Likewise. Order stock components will take 4 days of work and 5 days for delivery and Order custom components will take 5 days of work and 5 days for delivery. Reconfigure the CyClon schedule by entering the three finish-to-start lags. Part B. Upon further review the team recognize that they missed three finish-to-start lags. Procure prototype parts will involve only 6 days of work but it will take 5 days for the parts to be delivered. Likewise, Order stock components will take 4 days of work and 5 days for delivery and Order custom components will take 5 days of work and 5 days for delivery. Reconfigure the CyClon schedule by entering the three finish-to-start lags. What impact did these lags have on the original schedule? (Click to select) What impact did these lags have on the amount of work required to complete the project? (Click to select) Part C. Management is not happy with the schedule and wants the project completed as soon as possible. Unfortunately, they are not willing to approve additional resources. One team member pointed out that the network contained only finish-to-start relationships and that it might be possible to reduce project duration by creating start-to-start lags. After much deliberation the team concluded that the following relationships could be converted into start-to-start lags: . Procure prototype parts could start 6 days after the start of Design. Fabricate parts could start 9 days after the start of Design. Laboratory test could begin 1 day(s) after the start of Assemble prototype. Field test could start 5 days after the start of Laboratory test. Adjust design could begin 7 days after the start of Field test. Order stock and Order custom components could begin 5 days and 5 days, respectively, after Adjust design. Test unit could begin 10 days after the start of Assemble test production unit. Document results could start 3 days after the start of Test unit. Reconfigure the CyClon schedule by entering all nine start-to-start lags. What is the ES for Activity D? What is the LF for Activity H? What is the slack for Activity C? What is the slack for Activity H? What is the slack for Activity 17 What is the length of the project? What is the critical path? time periods
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started