Exercise 134 (Part Level Submission) Penner Builders contracted to build a high-rise for $28,300,000. Construction began in 2018 and is expected to be completed in
Exercise 134 (Part Level Submission)
Penner Builders contracted to build a high-rise for $28,300,000. Construction began in 2018 and is expected to be completed in 2020. Data for 2018 and 2019 are:
2018 | 2019 | |||
Costs incurred to date | $3,630,000 | $10,556,000 | ||
Estimated costs to complete | 14,520,000 | 9,744,000 |
Penner uses the percentage-of-completion method.
(c)
Make the journal entry to record the revenue and gross profit for 2019. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account titles and enter 0 for the amounts.)
Account Titles and Explanation | Debit | Credit |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started