Exercise 17-11 (Algo) Computing product cost per unit using plantwide method and activity-based costing LO P1, P3 Consider the following data for two products of
Exercise 17-11 (Algo) Computing product cost per unit using plantwide method and activity-based costing LO P1, P3
Consider the following data for two products of Vigano Manufacturing.
1. Using a plantwide overhead rate based on 6,250 direct labor hours, compute the total product cost per unit for each product. 2. Consider the following additional information about these two products. If activity-based costing is used to allocate overhead cost, (a) compute overhead activity rates, (b) allocate overhead cost to Product A and Product B and compute overhead cost per unit for each, and (c) compute product cost per unit for each.
Complete this question by entering your answers in the tabs below. Consider the following additional information about these two products. If activity-based costing is used to allocate overhead cost, (a) compute overhead activity rates, (b) allocate overhead cost to Product A and Product B and compute overhead cost per unit for each, and (c) compute product cost per unit for each. (Round your final answers to 2 decimal places.) ActivityMachinesetupPartshandlingQualityinspectionsTotalbudgetedoverheadBudgetedCost$25,000(20machinesetups)20,000(16,000parts)30,000(100inspections)$75,000ActivityDriver UnitInformationUnitsproducedDirectmaterialscostDirectlaborcostDirectlaborhoursProductA2,500units$35perunit$55perunit2perunitProductB500units$45perunit$65perunit2.50perunit Complete this question by entering your answers in the tabs below. Consider the following additional information about these two products. If activity-based costing is used to allocate overhead cost, (a) compute overhead activity rates, (b) allocate overhead cost to Product A and Product B and compute overhead cost per unit for each, and (c) compute product cost per unit for each. (Round your final answers to 2 decimal places.) ActivityMachinesetupPartshandlingQualityinspectionsTotalbudgetedoverheadBudgetedCost$25,000(20machinesetups)20,000(16,000parts)30,000(100inspections)$75,000ActivityDriver UnitInformationUnitsproducedDirectmaterialscostDirectlaborcostDirectlaborhoursProductA2,500units$35perunit$55perunit2perunitProductB500units$45perunit$65perunit2.50perunitStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started