Exercise 17-11 (Algo) Computing product cost per unit using plantwide method and activity-based costing LO P1, P3 Consider the following data for two products of Vigano Manufacturing Activity Budgeted Activity Driver Cost Machine setup $ 22,000 (20 machine setups) Parts handling 17,600 (16,000 parts) Quality inspections 26,400 (100 inspections) Total budgeted overhead $ 66,000 Unit Information Product A Product B Units produced 2,200 units 440 units Direct materials cost $ 32 per unit $ 42 per unit Direct labor cost $ 52 per unit $ 62 per unit Direct labor hours 2 per unit 2.50 per unit 1. Using a plantwide overhead rate based on 5,500 direct labor hours, compute the total product cost per unit for each product 2. Consider the following additional information about these two products, if activity-based costing is used to allocate overhead cost, (a) compute overhead activity rates. (b) allocate overhead cost to Product A and Product B and compute overhead cost per unit for each, and (c)compute product cost per unit for each. Actual Activity Unge Product Product B Setups 8 setups 12 setups Parts 10,000 parts 6,000 parts Inspections 40 inspections 60 inspections Complete this question by entering your answers in the tabs below. Required 1 Required 2 Using a plantwide overhead rate based on 5,500 direct labor hours, compute the total product cost per unit for each product. Per Unit Direct Materials Direct Labor Overhead Product Cost Der Unit Product A Producte Renu Required 2 > Preu 12 of 15 SH Next Required 1 Required 2 ok it ant ences Consider the following additional information about these two products. If activity-based costing is used to allocate overhead cost, (a) compute overhead activity rates, (b) allocate overhead cost to Product A and Product and compute overhead cost per unit for each, and (c) compute product cost per unit for each. (Round your final answers to 2 decimal places.) Show less a. Compute overhead activity rates Activity Activity Rate Machine setup per setup Parts handling per part Quality inspection per inspection b. Allocate overhead to Product A, B and compute overhead cost per unit Allocated Cost Activity Product A Products Machine setup Parts handling Quality inspection Total allocated cost Units produced Overhead cost per unit c. Product cost per unit using activity based costing Product Cost per Per Unit Unit Product A Product B