Exercise 3 table [ [ Activity , Predecessors,Duration ( days ) ] , [ A - Select office site,None, 3 ] , [ B

Exercise 3
\table[[Activity,Predecessors,Duration(days)],[A - Select office site,None,3],[B - Create org. and financial plan,None,5],[C - Determine personnel requirements,B,3],[D - Design facility,A, C,4],[E - Construct interior,D,8],[F - Select personnel to move,A, C,2],[G - Hire new employees,F,4],[H - Move records, key personnel, etc,F,2],[I - Train new personnel,E, G, H,3]]
Requirements:
Draw network diagrams for the above exercises.
Determine the critical path.
Calculate the total float(slack) and free float(slack).
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Pro SQL Server Wait Statistics

Authors: Enrico Van De Laar

1st Edition

1484211391, 9781484211397

More Books

Students also viewed these Databases questions

Question

LO1 Understand risk management and identify its components.

Answered: 1 week ago