Expert, Can you help me solve (a) to (d)? Thank You. Given the following table displaying the logical connections of activities and the time estimates

image text in transcribed
Expert, Can you help me solve (a) to (d)?
Thank You. image text in transcribed
Given the following table displaying the logical connections of activities and the time estimates of a construction project: a Precedence 10 Activity A B D E F G H Time (Weeks) m b 4 4 5 11 11 1 7 13 7 8 9 12 15 18 9 12 15 4 7 10 1 4 7 A A C,D B.F E,G a. Construct the network diagram for the project. Also, calculate the EST and LST of the events and mark on the diagram. b. Calculate the te, s-, TF, FF and IF. (Show all your calculation steps). (16 marks) (8 marks) c. Determine the completion time(Te) and standard deviation(St) of the project. (2 marks) d. Determine the probability of the project's completion in 32 weeks and in 36 weeks. (4 marks) Given the following table displaying the logical connections of activities and the time estimates of a construction project: a Precedence 10 Activity A B D E F G H Time (Weeks) m b 4 4 5 11 11 1 7 13 7 8 9 12 15 18 9 12 15 4 7 10 1 4 7 A A C,D B.F E,G a. Construct the network diagram for the project. Also, calculate the EST and LST of the events and mark on the diagram. b. Calculate the te, s-, TF, FF and IF. (Show all your calculation steps). (16 marks) (8 marks) c. Determine the completion time(Te) and standard deviation(St) of the project. (2 marks) d. Determine the probability of the project's completion in 32 weeks and in 36 weeks. (4 marks)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management and Cost Accounting

Authors: Alnoor Bhimani, Charles T. Horngren, Srikant M. Datar, Madhav V. Rajan

6th edition

1292063467, 978-1292063461

More Books

Students also viewed these Accounting questions

Question

=+b) Should the company send the fact-finding trip? Explain.

Answered: 1 week ago