Question
Explain the most suitable link type in Microsoft Project for the following conditions, and justify your answer.: 1. You are developing a project with a
Explain the most suitable link type in Microsoft Project for the following conditions, and justify your answer.: 1. You are developing a project with a main task A and multiple tasks B. Tasks B cannot be completed until task A begins. Task A will start before and take longer than tasks B. A link needs to be created from the main task A to each of the tasks B. 2. In a construction project, all construction materials need to be supplied to the team before the construction work starts. A link needs to be created from the delivery of the construction materials to the construction task
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started