Question:
\fACT Duration ESD EFD LSD LFD TF FF A 5 B J IOnmon M V b. Find all the paths and path lengths through this project network. Which of these paths is a critical path? c. Will Ken be able to meet his deadline if no delays occur? d. To stay on schedule, which activities he should focus most of his attention on