Fact Pattern: On January 1 , Year 1 , Big Co . enters into a contract with a customer to build a bridge on the

Fact Pattern:
On January 1, Year 1, Big Co. enters into a contract with a customer to build a bridge on the customers land for $2,500,000. The construction of the bridge is expected to be completed at the end of Year 3. Big determines that the progress toward completion of the bridge is reasonably measurable using the input method based on costs incurred. At contract inception, Big estimates that the expected total cost of construction will be $1,700,000. Below are the (1) actual costs incurred during each year, (2) expected costs to complete the construction, and (3) amounts billed to the customer:
Year 1
Year 2
Year 3
Costs incurred each year
$ 700,000
$500,000
$800,000
Costs expected in the following years
1,300,000
675,000
0
Amounts billed to (and paid by) the customer each year
700,000
950,000
850,000
What amount of revenue on this contract is recognized by Big in its Year 1 income statement?
$875,000
$175,000
$700,000
$650,000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Survey of Accounting

Authors: Edmonds, old, Mcnair, Tsay

2nd edition

9780077392659, 978-0-07-73417, 77392655, 0-07-734177-5, 73379557, 978-0073379555

More Books

Students also viewed these Accounting questions