Question
1 Approved Answer

On February 1, 2024, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2024,

 image text in transcribed 
 
image text in transcribed
 
image text in transcribed
 
image text in transcribed
 
image text in transcribed

On February 1, 2024, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2024, costs of $2,120,000 were incurred, with estimated costs of $4,120,000 yet to be incurred. Billings of $2,644,000 were sent, and cash collected was $2,370,000. In 2025, costs incurred were $2,644,000 with remaining costs estimated to be $3,780,000. 2025 billings were $2,894,000, and $2,595,000 cash was collected. The project was completed in 2026 after additional costs of $3,920,000 were incurred. The company's fiscal year-end is December 31. This project does not qualify for revenue recognition over time. Required: 1. Calculate the amount of revenue and gross profit or loss to be recognized in each of the three years. 2a. Prepare journal entries for 2024 to record the transactions described (credit "Cash, Materials, etc." for construction costs incurred). 2b. Prepare journal entries for 2025 to record the transactions described (credit "Cash, Materials, etc." for construction costs incurred). 3a. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2024. 3b. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2025. Complete this question by entering your answers in the tabs below. Req 1 Req 2A Req 28 Req 3A Req 38 Calculate the amount of revenue and gross profit or loss to be recognized in each of the three years. Note: Loss amounts should be indicated with a minus sign. Leave no cells blank. Year Revenue recognized 2024 2025 2026 Total Gross profit (loss) recognized Rg1 Req 2A > Assessment Tool Frame On February 1, 2024, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2024, costs of $2,120,000 were incurred, with estimated costs of $4,120,000 yet to be incurred. Billings of $2,644,000 were sent, and cash collected was $2,370,000. In 2025, costs incurred were $2,644,000 with remaining costs estimated to be $3,780,000. 2025 billings were $2,894,000, and $2,595,000 cash was collected. The project was completed in 2026 after additional costs of $3,920,000 were incurred. The company's fiscal year-end is December 31. This project does not qualify for revenue recognition over time. Required: 1. Calculate the amount of revenue and gross profit or loss to be recognized in each of the three years. 2a. Prepare journal entries for 2024 to record the transactions described (credit "Cash, Materials, etc." for construction costs incurred). 2b. Prepare journal entries for 2025 to record the transactions described (credit "Cash, Materials, etc." for construction costs incurred). 3a. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2024. 3b. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2025. Complete this question by entering your answers in the tabs below. Req 1 Req 2A Req 28 Req 3A Req 38 Prepare journal entries for 2024 to record the transactions described (credit "Cash, Materials, etc." for construction costs incurred). Note: If no entry is required for a transaction/event, select "No journal entry required" in the first account field. View transaction list Journal entry worksheet 1 2 3 4 Record the construction costs. Note: Enter debits before credits. Year 2024 General Journal Debit Credit On February 1, 2024, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2024, costs of $2,120,000 were incurred, with estimated costs of $4,120,000 yet to be incurred. Billings of $2,644,000 were sent, and cash collected was $2,370,000. In 2025, costs incurred were $2,644,000 with remaining costs estimated to be $3,780,000. 2025 billings were $2,894,000, and $2,595,000 cash was collected. The project was completed in 2026 after additional costs of $3,920,000 were incurred. The company's fiscal year-end is December 31. This project does not qualify for revenue recognition over time. Required: 1. Calculate the amount of revenue and gross profit or loss to be recognized in each of the three years. 2a. Prepare journal entries for 2024 to record the transactions described (credit "Cash, Materials, etc." for construction costs incurred). 2b. Prepare journal entries for 2025 to record the transactions described (credit "Cash, Materials, etc." for construction costs incurred). 3a. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2024. 3b. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2025. Complete this question by entering your answers in the tabs below. Req 1 Req 2A Req 28 Req 3A Req 38 Prepare journal entries for 2025 to record the transactions described (credit "Cash, Materials, etc." for construction costs incurred).. Note: If no entry is required for a transaction/event, select "No journal entry required" in the first account field. View transaction list Journal entry worksheet < 2 3 4 Record the construction costs. Note: Enter debits before credits Year 2025 General Journal Debit Credit On February 1, 2024, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2024, costs of $2,120,000 were incurred, with estimated costs of $4,120,000 yet to be incurred. Billings of $2,644,000 were sent, and cash collected was $2,370,000. In 2025, costs incurred were $2,644,000 with remaining costs estimated to be $3,780,000. 2025 billings were $2,894,000, and $2,595,000 cash was collected. The project was completed in 2026 after additional costs of $3,920,000 were incurred. The company's fiscal year-end is December 31. This project does not qualify for revenue recognition over time. Required: 1. Calculate the amount of revenue and gross profit or loss to be recognized in each of the three years. 2a. Prepare journal entries for 2024 to record the transactions described (credit "Cash, Materials, etc." for construction costs incurred). 2b. Prepare journal entries for 2025 to record the transactions described (credit "Cash, Materials, etc." for construction costs incurred). 3a. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2024. 3b. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2025. Complete this question by entering your answers in the tabs below. Req 1 Req 2A Req 28 Req 3A Req 38 Prepare a partial balance sheet to show the presentation of the project as of December 31, 2024. Note: Do not round intermediate calculations. Round your answers to the nearest dollar amount. Current assets: Balance Sheet At December 31, 2024 Current abilities: < Req 28 Req 38 > On February 1, 2024, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2024, costs of $2,120,000 were incurred, with estimated costs of $4,120,000 yet to be incurred. Billings of $2,644,000 were sent, and cash collected was $2,370,000. In 2025, costs incurred were $2,644,000 with remaining costs estimated to be $3,780,000. 2025 billings were $2,894,000, and $2,595,000 cash was collected. The project was completed in 2026 after additional costs of $3,920,000 were incurred. The company's fiscal year-end is December 31. This project does not qualify for revenue recognition over time. Required: 1. Calculate the amount of revenue and gross profit or loss to be recognized in each of the three years. 2a. Prepare journal entries for 2024 to record the transactions described (credit "Cash, Materials, etc." for construction costs incurred). 2b. Prepare journal entries for 2025 to record the transactions described (credit "Cash, Materials, etc." for construction costs incurred). 3a. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2024. 3b. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2025. Complete this question by entering your answers in the tabs below. Req 1 Reg 2A Req 28 Req 3A Req 38 Prepare a partial balance sheet to show the presentation of the project as of December 31, 2025. Note: Do not round intermediate calculations. Round your answers to the nearest dollar amount. Current assets Balance Sheet At December 31, 2025 Current liablities:

Step by Step Solution

There are 3 Steps involved in it

Step: 1

To solve this we need to handle the construction contract using the completed contract method as rev... blur-text-image
Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting The Impact On Decision Makers

Authors: Gary A. Porter, Curtis L. Norton

2nd Edition

0030270995, 978-0030270994

More Books

Students explore these related Accounting questions