Question
1 Approved Answer
Figure 2 shows a cost-loaded schedule of a project. Which of the following combinations show the correct cost of work performed in Week 3 and
Figure 2 shows a cost-loaded schedule of a project. Which of the following combinations show the correct cost of work performed in Week 3 and Week 9 ? Week 3=$10,700, Week 9=$18,000 Week 3=$9,800, Week 9=$18,000 Week 3=$9,800, Week 9=$14,300 D Week3 =$10,700, Week 9=$14,300