Fill the blanks. You will assume sales tax at 6% and overhead & profit at 20%. ITEM QUANTITY MATERIALS LABOR EQUIPMENT TOTAL $/UNIT COST LHR/UNIT

Fill the blanks. You will assume sales tax at 6% and overhead & profit at 20%.

ITEM QUANTITY MATERIALS LABOR EQUIPMENT TOTAL
$/UNIT COST LHR/UNIT LHR $/LHR COST $/LHR COST
02000 EXISTING CONDITIONS
02400 Demolition
Saw cut curb 5 ft - - 19.00 - - -
Remove curb 30 ft - - 19.00 - - -
- - - -
Sale Tax 0.00% - -
- - - - -
03000 CONCRETE
03200 Rebar
Footings
#4-20' rebar 52 ea - - 19.00 - - -
#5-3'6" rebar 32 ea - - 19.00 - - -
#6-5' rebar 66 ea - - 19.00 - - -
#5-9"x27" dowels 90 ea - - 19.00 - - -
#6-9"x27" dowels 12 ea - - 19.00 - - -
Masonry
#4-20' rebar 130 ea - - 19.00 - - -
#5-4' rebar 90 ea - - 19.00 - - -
#5-5'6" rebar 360 ea - - 19.00 - - -
#6-4' rebar 12 ea - - 19.00 - - -
#6-5'6" rebar 48 ea - - 19.00 - - -
#3-8"x8" square ties 58 ea - - 19.00 - - -
#6-6'-6" rebar 12 ea - - 19.00 - - -
#6-8'-9" rebar 23 ea - - 19.00 - - -
#6-12'-6" rebar 12 ea - - 19.00 - - -
5/8"x6" anchor bolts 90 ea - - 19.00 - - -
5/8" washer 90 ea - - 19.00 - - -
5/8" nuts 90 ea - - 19.00 - - -
- - - - -
Sale Tax 0.00% - -
- - - - -
03300 Footings and Foundation--Labor
Pour 12"x24" cont footing 17.0 cyd - - 19.00 - - -
Pour 48"x48"x12 footing 1.2 cyd - - 19.00 - - -
12" high forms 483 ft - - 19.00 - - -
Pour 66"x66"x18" footing 5 cyd - - 19.00 - - -
24" high forms 132 sft - - 19.00 - - -
- - - - -
Sale Tax 0.00% - -
- - - - -
03310 Footings and Foundation--Concrete
12"x24" cont footing (F1) 17.0 cyd - - 19.00 - - -
48"x48"x12 footing (F3) 1.2 cyd - - 19.00 - - -
66"x66"x18" footing (F2) 5.0 cyd - - 19.00 - - -
- - - - -
Sale Tax 0.00% - -
- - - - -
03320 Slab/Floor--Labor
Pour 5" conc slab 47.5 cyd - - 19.00 - - -
Finish conc slab 3,064 sft - - 19.00 - - -
Forms at openings 33 ft - - 19.00 - - -
1/4"x1" sawcut 194 ft - - 19.00 - - -
1/4"x1" caulk 194 ft - - 19.00 - - -
- - - - -
Sale Tax 0.00% - -
- - - - -
03330 Slab/Floor--Concrete
5" conc slab 47.5 cyd - - 19.00 - - -
- - - - -
Sale Tax 0.00% - -
- - - - -

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managerial Accounting

Authors: Ray H. Garrison, Eric W. Noreen, Peter C. Brewer

13th Edition

978-0073379616, 73379611, 978-0697789938

More Books

Students also viewed these Accounting questions