Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Finance has asked for a preliminary report on how much capital will be needed to purchase the units needed to complete these orders. Using the

image text in transcribed

Finance has asked for a preliminary report on how much capital will be needed to purchase the units needed to complete these orders. Using the MRP matrices and the notes provided, calculate the capital costs per period and total for the quarter associated with the schedule you have constructed. There are no capital costs for finished samplers. Inventory holding costs are approximately the same for each lower level item and run about $0.50 per unit per period. There are no inventory costs for the final samplers themselves. Jody also needs to estimate the costs incurred from holding inventory over the quarter.

image text in transcribed

image text in transcribed

Item Master File Item On Hand Lead Time Lot Size Scheduled Receipts Unit Manufacturing /Purchasing Cost $6.00 9 2 1 0 15 1 1 $6.00 0 250 1 10 $1.00 0 301 2 75 $1.00 0 Northwest Grunge Sampler Deep South Hooch Sampler Walla Walla Mud Mt. Hood Dredge Tacoma Terror Tuscaloosa Tornado Meridian Mothball Augusta Augsbarge Labels Boxes 350 40 $0.50 0 15 1 $0.50 0 250 2 20 $0.50 0 5 1 40 $0.50 0 257 611 2 2 100 91 $0.01 $0.10 0 0 Finance has asked for a preliminary report on how much capital will be needed to purchase the units needed to complete these orders. Using the MRP matrices and the notes provided, calculate the capital costs per period and total for the quarter associated with the schedule you have constructed. There are no capital costs for finished samplers. Inventory holding costs are approximately the same for each lower level item and run about $0.50 per unit per period. There are no inventory costs for the final samplers themselves. Jody also needs to estimate the costs incurred from holding inventory over the quarter. Period LLC: 0 LT: 1 PD 2 3 4 5 6 8 9 10 11 12 Item: Deep South Lot size: 1 Gross requirements Scheduled receipts Projected on hand Net requirements Planned order receipts Planned order releases 0 0 0 0 0 0 0 0 0 0 0 0 0 D 0 0 0 0 0 0 0 0 0 0 01 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Subcontract $0.00 Period LLC: 1 LT: 1 PD 2 4 6 9 3 0 5 0 7 01 8 0 10 0 11 0 12 0 0 D 0 0 0 0 0 Item: Agusta Aug Lot size: 40 Gross requirements Scheduled receipts Projected on hand Net requirements Planned order receipts Planned order releases Capital Costs Expediting Cost 0 0 0 0 0 0 0 0 0 D 0 01 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 D 0 0 0 $0.00 0 $0.00 0 0 $0.00 0 S0.00 $0.00 $0.00 $0.00 S0.00 $0.00 $0.00 Period LLC: 1 LT:2 PD 4 2 0 3 0 5 0 6 6 0 7 0 8 0 9 0 10 0 11 0 12 0 0 0 0 0 0 0 0 0 0 Item: Mer. Mb Lot size: 20 Gross requirements Scheduled receipts Projected on hand Net requirements Planned order receipts Planned order releases Capital Costs Expediting Cost 0 0 0 0 0 D 0 0 0 0 0 0 0 0 0 $0.00 01 0 0 0 01 0 0 0 0 $0.00 0 0 0 $0.00 0 0 0 0 0 $0.00 0 0 $0.00 0 0 0 $0.00 0 $0.00 0 $0.00 0 0 S0.00 0 S0.00 $0.00 $0.00 $0.00 Period LLC: LT: 1 PD 2 3 41 4 91 10 11 1 0 5 0 6 0 7 0 8 0 12 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Item: T Tornado Lot size: 1 Gross requirements Scheduled receipts Projected on hand Net requirements Planned order receipts Planned order releases Capital Costs Expediting Cost 0 0 0 0 0 0 0 0 D 0 0 0 0 0 0 0 0 0 0 0 $0.00 0 S0.00 0 0 $0.00 0 0 $0.00 0 0 $0.00 0 0 S0.00 0 0 $0.00 0 0 S0.00 0 $0.00 0 0 $0.00 0 0 S0.00 0 0 $0.00 $0.00 Period PD 21 4 5 6 7 8 9 10 11 12 Item: Grunge LLC: 0 Lot size: 1 LT: 2 Gross requirements Scheduled receipts Projected on hand Net requirements Planned order receipts Planned order releases 0 0 D 0 0 0 0 0 D 0 0 0 0 0 D 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Subcontract $0.00 Period PD 1 6 7 81 9 2 0 3 0 4 0 5 0 10 0 11 0 12 0 0 0 0 0 0 0 D 0 0 0 3 Item: WW Mud LLC: 1 Lot size: 10 LT: 1 Gross requirements Scheduled receipts Projected on hand Net requirements Planned order receipts Planned order releases Capital Costs - Expediting Cost 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 $0.00 0 S0.00 $0.00 $0.00 S0.00 S0.00 S0.00 S0.00 S0.00 $0.00 Period PD 1 $ 9 12 2 D 3 3 D 4 0 6 0 7 ol 8 0 10 0 11 0 D D 0 0 0 0 0 0 0 0 0 0 0 0 0 Item: Mt Dredge LLC: 1 Lot size: 75 LT: 2 Gross requirements Scheduled receipts Projected on hand Net requirements Planned order recipts Planned order releases Capital Costs Expediting Cost 0 0 0 0 0 0 0 0 01 0 U 0 0 0 0 0 0 D 0 0 0 0 0 D $0,00 0 0 D $0.00 0 D 0 0 0 S0.00 D $0.00 0 D 50,00 $0.00 S0.00 0.00 0.00 S0.00 ).00 50.00 $0.00 Period PI) 3 6 7 1 0 2 0 4 0 5 0 8 0 9 0 10 0 11 0 12 0 0 0 0 0 0 0 0 0 0 0 0 Item: T Terror LLC: 1 Lot size: 40 LT: 1 Gross requirements Scheduled receipts Projected on hand Nct requirements Planned order receipts Planned order releases Capital Costs Expediting Cost 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 D D $0.00 0 0 0 D 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 S0.00 D $0.00 0 0 S0.00 0 S0.00 $0.00 S0.00 50.00 50.00 50.00 S0.00 $0.00 Item Master File Item On Hand Lead Time Lot Size Scheduled Receipts Unit Manufacturing /Purchasing Cost $6.00 9 2 1 0 15 1 1 $6.00 0 250 1 10 $1.00 0 301 2 75 $1.00 0 Northwest Grunge Sampler Deep South Hooch Sampler Walla Walla Mud Mt. Hood Dredge Tacoma Terror Tuscaloosa Tornado Meridian Mothball Augusta Augsbarge Labels Boxes 350 40 $0.50 0 15 1 $0.50 0 250 2 20 $0.50 0 5 1 40 $0.50 0 257 611 2 2 100 91 $0.01 $0.10 0 0 Finance has asked for a preliminary report on how much capital will be needed to purchase the units needed to complete these orders. Using the MRP matrices and the notes provided, calculate the capital costs per period and total for the quarter associated with the schedule you have constructed. There are no capital costs for finished samplers. Inventory holding costs are approximately the same for each lower level item and run about $0.50 per unit per period. There are no inventory costs for the final samplers themselves. Jody also needs to estimate the costs incurred from holding inventory over the quarter. Period LLC: 0 LT: 1 PD 2 3 4 5 6 8 9 10 11 12 Item: Deep South Lot size: 1 Gross requirements Scheduled receipts Projected on hand Net requirements Planned order receipts Planned order releases 0 0 0 0 0 0 0 0 0 0 0 0 0 D 0 0 0 0 0 0 0 0 0 0 01 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Subcontract $0.00 Period LLC: 1 LT: 1 PD 2 4 6 9 3 0 5 0 7 01 8 0 10 0 11 0 12 0 0 D 0 0 0 0 0 Item: Agusta Aug Lot size: 40 Gross requirements Scheduled receipts Projected on hand Net requirements Planned order receipts Planned order releases Capital Costs Expediting Cost 0 0 0 0 0 0 0 0 0 D 0 01 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 D 0 0 0 $0.00 0 $0.00 0 0 $0.00 0 S0.00 $0.00 $0.00 $0.00 S0.00 $0.00 $0.00 Period LLC: 1 LT:2 PD 4 2 0 3 0 5 0 6 6 0 7 0 8 0 9 0 10 0 11 0 12 0 0 0 0 0 0 0 0 0 0 Item: Mer. Mb Lot size: 20 Gross requirements Scheduled receipts Projected on hand Net requirements Planned order receipts Planned order releases Capital Costs Expediting Cost 0 0 0 0 0 D 0 0 0 0 0 0 0 0 0 $0.00 01 0 0 0 01 0 0 0 0 $0.00 0 0 0 $0.00 0 0 0 0 0 $0.00 0 0 $0.00 0 0 0 $0.00 0 $0.00 0 $0.00 0 0 S0.00 0 S0.00 $0.00 $0.00 $0.00 Period LLC: LT: 1 PD 2 3 41 4 91 10 11 1 0 5 0 6 0 7 0 8 0 12 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Item: T Tornado Lot size: 1 Gross requirements Scheduled receipts Projected on hand Net requirements Planned order receipts Planned order releases Capital Costs Expediting Cost 0 0 0 0 0 0 0 0 D 0 0 0 0 0 0 0 0 0 0 0 $0.00 0 S0.00 0 0 $0.00 0 0 $0.00 0 0 $0.00 0 0 S0.00 0 0 $0.00 0 0 S0.00 0 $0.00 0 0 $0.00 0 0 S0.00 0 0 $0.00 $0.00 Period PD 21 4 5 6 7 8 9 10 11 12 Item: Grunge LLC: 0 Lot size: 1 LT: 2 Gross requirements Scheduled receipts Projected on hand Net requirements Planned order receipts Planned order releases 0 0 D 0 0 0 0 0 D 0 0 0 0 0 D 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Subcontract $0.00 Period PD 1 6 7 81 9 2 0 3 0 4 0 5 0 10 0 11 0 12 0 0 0 0 0 0 0 D 0 0 0 3 Item: WW Mud LLC: 1 Lot size: 10 LT: 1 Gross requirements Scheduled receipts Projected on hand Net requirements Planned order receipts Planned order releases Capital Costs - Expediting Cost 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 $0.00 0 S0.00 $0.00 $0.00 S0.00 S0.00 S0.00 S0.00 S0.00 $0.00 Period PD 1 $ 9 12 2 D 3 3 D 4 0 6 0 7 ol 8 0 10 0 11 0 D D 0 0 0 0 0 0 0 0 0 0 0 0 0 Item: Mt Dredge LLC: 1 Lot size: 75 LT: 2 Gross requirements Scheduled receipts Projected on hand Net requirements Planned order recipts Planned order releases Capital Costs Expediting Cost 0 0 0 0 0 0 0 0 01 0 U 0 0 0 0 0 0 D 0 0 0 0 0 D $0,00 0 0 D $0.00 0 D 0 0 0 S0.00 D $0.00 0 D 50,00 $0.00 S0.00 0.00 0.00 S0.00 ).00 50.00 $0.00 Period PI) 3 6 7 1 0 2 0 4 0 5 0 8 0 9 0 10 0 11 0 12 0 0 0 0 0 0 0 0 0 0 0 0 Item: T Terror LLC: 1 Lot size: 40 LT: 1 Gross requirements Scheduled receipts Projected on hand Nct requirements Planned order receipts Planned order releases Capital Costs Expediting Cost 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 D D $0.00 0 0 0 D 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 S0.00 D $0.00 0 0 S0.00 0 S0.00 $0.00 S0.00 50.00 50.00 50.00 S0.00 $0.00

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Audit Report Chavarria Dinne And Lamey LLC Contract Deliverables Office Of Inspector U.S Department Of The Interior

Authors: United States Department Of The Interior

1st Edition

1511678526, 978-1511678520

More Books

Students also viewed these Accounting questions

Question

=+b. What is the probability that reaction time exceeds 0.5 sec?

Answered: 1 week ago

Question

1. Discuss the four components of language.

Answered: 1 week ago

Question

f. What stereotypes were reinforced in the commercials?

Answered: 1 week ago