Financial appraisal of investment projects The NextGen project is an example of how the financial appraisal of an investment project is conducted at Cengage Learning.

Financial appraisal of investment projects

The NextGen project is an example of how the financial appraisal of an investment project is conducted at Cengage Learning. The NextGen project passed through several stages of the capital investment process, which required the finance team to evaluate if and to what extent the project would drive incremental revenue or contribute toward revenue preservation.

Instructions: Review the following stages of the financial appraisal process for this project and complete missing information as needed.

Project Overview

The innovation team proposed a digital learning platform that will create a personalized learning experience for each student. The platform consists of a set of flexible tools that will allow students to customize the technology to suit their personal learning needs. The executive team believes that the value proposition offered by the NextGen project will be one of a kind in the digital learning space and give the company a first-mover advantage. The finance team conducted the financial appraisal of the project to evaluate if and to what extent the project would drive incremental revenue or contribute toward revenue preservation.

Relevant Cash Flows

The finance team scheduled a series of meetings to discuss the different aspects of the project analysis. Sanford Tassel, Senior Vice President, Finance and Operations, Dikran Yapoujian, Vice President, Finance and other members of the finance-decision support team held a series of discussions. Some excerpts from their discussions follow:

From: Yapoujian, Dikran

To: Tassel, Sanford

Cc: Buzzard, Chris; Muhleman, Purlen

Subject: Relevant cash flows

Attached: Data.xls

Hey Sanford,

Ive been working with the team to evaluate the NextGen product in the capital approval pipeline. Ive crafted the valuation model taking into consideration our standard underlying assumptions, the cumulative capital outlay, and the estimations of the cash flows for this long-term strategic initiative.

Chris and Purlen worked through the revenue estimates, accounting for the digital solutions developed, the companys average textbook business, and related augmented revenues through the NextGen learning platform and the overall impact on the business by accelerating the adoption of digital products in the education marketplace. It is also expected to prevent the loss of sales on the businesss legacy products.

Here are my thoughts:

In addition to being strategic to Cengage, the project seems viable economically. The technology used in the project is evolutionary in nature, restricting us to work with a relevant time horizon of six years and to ignore any cash flows after the sixth year.

We would need to immediately approve a capital allocation of $1.70 million to jump-start the project. In addition, we would need to capitalize another $20.5 million almost equally for the next three years. These expenses will be incurred on an after-tax basis. The first year of the project is unlikely to bring any additional revenues, but from second year, we should see revenues increase by $1.800 million. Our preliminary estimates also show revenues growing to $9.700 million in year 2, $19.300 million in year 3, $22.800 million in year 4, and $24.600 million in year 5.

I am also attaching some information the team used for the cash flow valuation. See you later to go over the numbers.

Cheers,

Dikran

Attachment: Data.xls

(All dollar values in millions)

A

B

1 Capitalized expenses $20.5 (spread over 3 years)
2 Non-cash(depreciable) expenses $3.400
3 Operating costs as a percentage of revenues Year 1: 141%
Year 2: 33%
Year 3: 22%
Year 4: 22%
Year 5: 24%
4 Taxes 40%

The analysts on the team created pro forma estimates of the expected cash flows that the project is likely to generate and also discussed some assumptions:

Revenue estimates are based on the expectation of a higher price point resulting from a more robust product.
Operating expenses include internal labor, maintenance, overhead expense, and cost avoidance from being able to ramp down spending on existing platforms.
The capitalized expenses include the costs of platform development, content creation, internal and external labor, computers, facility investment, and so on. These expenses are amortizable and depreciable over the first three of the six years of the projects expected life. They are recognized separately from the normal depreciation and amortization expenses.
These capital expenses will be deducted from the projects annual cash flow from operations to derive at the projects total expected cash flows.

Complete the following cash flow analysis based on the information provided. (Note: Express all values in millions of dollars and round all values to three decimal places. Use a minus (-) sign to indicate any negative amount.)

Year 0

Year 1

Year 2

Year 3

Year 4

Year 5

Revenues 0
Less: Operating expenses
Less: Depreciation & Amortization
Operating Income
Less: Tax
Plus: Non-cash expenses
Operating Cash Flow
Less: Capitalized expenses 7.300 6.600 6.600
Total Cash Flow

Financing Costs

The finance team got together to discuss the financing costs of the project. The following is an excerpt of their discussion. Read the dialogue and fill in the missing word or words.

DIKRAN: Should we use the companys WACC or use the beta of a comparable project when applying a cost of capital to this project?

SANFORD: We calculate our WACC on an annual basis based on the companys capital structure for the fiscal year. All of our investments are treated as cash investments so that we can fairly compare all initiatives based on their value proposition. This is a one-of-a-kind project in the ed tech space, and we believe that it will drive incremental revenues and contribute to the preservation of revenue for Cengages existing products. The project also seems to align with the reinvestment objectives of our private equity owners.

DIKRAN: Sounds good. We also calculate our applicable tax rates annually, and considering the digital landscape of this project, we necessarily need to use different tax rates based on the different states in which we operate. I guess it is fair to apply a standard tax rate in the valuation of the project cash flows.

SANFORD: Lets use our standard WACC of 12%. Ill see you soon to discuss the valuation of the project.

Project Evaluation

The analysts in the team run the numbers and hand over the evaluation to Sanford. Complete the data in the report. (Note: Round your input values to three decimal places and your output values to two decimal places. Use a minus (-) sign to indicate any negative amount.)

Year 0

Year 1

Year 2

Year 3

Year 4

Year 5

PV of cash flows
NPV of the project
IRR of the project
Payback period 3.30 years

The Accept/Reject Recommendation

The project proposal with supporting data was presented to the CFO and the board. After discussion and scrutiny of the assumptions in the report, the board is most likely to the project because of which of the following reasons? Check all that apply.

The management team believes that this project will lead the transition toward becoming a digital-first company.

Management feels positive about the project, and their instincts say to go for it.

Management is not confident about the digital innovation teams track record.

The project has a shelf-life shorter than the payback period of the investment

Please show your work in detail

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Markets And Institutions

Authors: Anthony Saunders, Marcia Cornett

7th Edition

1259919714, 978-1259919718

More Books

Students also viewed these Finance questions

Question

What is a dynamic scheduling problem?

Answered: 1 week ago