Question

1 Approved Answer

Find a list that produces the optimal schedule; shown, when the list - processing algorithm is applied to this list. ( Assume that the tasks

Find a list that produces the optimal schedule; shown, when the list-processing algorithm is applied to this list. (Assume that the tasks are independent).
What schedule is obtained when the decreasing-time-list algorithm is applied to this list?
Machine 1: T1,T2,T3
Machine 2: T4,T5, idle 28 to 32
Machine 1: T4,T2,T1
Machine 2: T3,T5, idle 28 to 32
Machine 1: T2,T4,T5
Machine 2: T1,T3, idle 26 to 31
Machine 1: T1,T4,T1
Machine 2: T5,T3, idle 22 to 29
What completion time is obtained when the decreasing-time-list algorithm is applied to this list? Give your answer as a whole number.
completion time:
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Pro SQL Server Wait Statistics

Authors: Enrico Van De Laar

1st Edition

1484211391, 9781484211397

More Books

Students also viewed these Databases questions

Question

2 What are the psychological stages of coping with change?

Answered: 1 week ago

Question

6 Why is change considered a central aspect of HRM practice?

Answered: 1 week ago