Find planned value The original labor budget for the project is $105,200, based on 2,104 budgeted hours at the standard IT department rate of $50/hr.
Find planned value
The original labor budget for the project is $105,200, based on 2,104 budgeted hours at the standard IT department rate of $50/hr. Any necessary equipment will be paid for out of a state technology grant program whose funds are expiring this fiscal year.
The project started the first Monday of March, and the goal is to finish by the end of the city's fiscal year, which runs July 1-June 30.
Budget | % Complete | Expenditures | |||
Hours | Dollars | Hours | Dollars | ||
Utilities | 352 | $17,600.00 | 26.23% | 90 | $4,500.00 |
Create database tables | 48 | $2,400.00 | 100% | 45 | $2,250.00 |
Data cleanup and import | 65 | $1,600.00 | 54% | 15 | $750.00 |
Customization of utility module | 208 | $10,400.00 | 13% | 30 | $1,500.00 |
Integration with water meter system | 40 | $2,000.00 | 0% | 0 | - |
Testing | 24 | $1,200.00 | 0% | 0 | - |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started