Question
Find the critical path and the project completion time for the following list of activities. Calculate the probabilities of completing the following project in 13
- Find the critical path and the project completion time for the following list of activities. Calculate the probabilities of completing the following project in
- 13 days or more
- 11 days or less
- between 12 and 14 days
Activity | Immediate Predecessor | Optimistic Duration | Most Probable Duration | Pessimistic Duration |
A | - | 1 | 3 | 5 |
B | - | 2 | 4 | 6 |
C | A, B | 2 | 4 | 5 |
D | A, B | 3 | 5 | 7 |
E | C, D | 1 | 2 | 10 |
Step by Step Solution
3.46 Rating (149 Votes )
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get StartedRecommended Textbook for
Project Management A Managerial Approach
Authors: Jack R. Meredith, Samuel J. Mantel,
7th Edition
470226218, 978-0470226216
Students also viewed these General Management questions
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
View Answer in SolutionInn App