Find the earliest start time ( ES ) of the activity D in the following network: Activity Predecessor Time A - - - 8 B

Find the earliest start time (ES) of the activity D in the following network:
Activity Predecessor Time
A ---8
B ---3
C A 7
D A, B 4
E C, D 2
Answer:
10 Incorrect Response (8)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Business and Administrative Communication

Authors: Kitty o. locker, Donna s. kienzler

10th edition

77830105, 978-0077830106, 978-0073403182

More Books

Students also viewed these General Management questions