Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Find the following: 1. Using the provided figure, plot the time needed each activity and determine the critical path. 2. Total completion time (in days).

image text in transcribed

image text in transcribedimage text in transcribed

Find the following:

1. Using the provided figure, plot the time needed each activity and determine the critical path.

2. Total completion time (in days).

3. If the project will start on July 1, 2023, when will be the completion date?

Critical path identification: In the table below are the activities of a certain engineering project and time (in days) n activities. Early Start (ES): It is equal to the Early Finish to the activity's precedent. If it has more than one precedent, the highest value is taken. Early Finish (EF): It is equal to the Early Start of the activity plus its duration (t). EF = ES + t. Late Start (LS): It is equal to the Late Finish minus its duration (t). LS = LF - t. Late Finish (LF): It is equal to the late start of the activity that follows. If it has more than one successor, the lowest value is taken. Slack (S) or Total Float: It can be calculated in two ways. S = LS - ES = LF - EF. Activities with zero slack make up the critical path and are highlighted in green. Free Float: Is measured by subtracting the early finish (EF) of the activity from the early start (ES) of the successor activity. Represents the amount of time that a schedule activity can be delayed without delaying the early start date of any immediate successor activity within the network path

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Information Technology Project Management

Authors: Kathy Schwalbe

6th Edition

978-111122175, 1133172393, 9780324786927, 1111221758, 9781133172390, 324786921, 978-1133153726

More Books

Students also viewed these General Management questions

Question

How does a tax exclusion differ from a tax deduction?

Answered: 1 week ago