Find the project completion time for the following list of activities. Activity Immediate Predecessor Completion time A - 3 B - 2 C A, 6
Find the project completion time for the following list of activities. Activity Immediate Predecessor Completion time A - 3 B - 2 C A, 6 D A, B 4 E C, D 7 F E 4 G E,F 6 H G 9 I H 3