Find:Job sequence, average flow time, average da job Processing time( days) Due Date( days) a 10 10 b 5 15 c 7 17 d 8
- Find:Job sequence, average flow time, average da
job | Processing time( days) | Due Date( days) |
a | 10 | 10 |
b | 5 | 15 |
c | 7 | 17 |
d | 8 | 20 |
e | 6 | 22 |
f | 9 | 21 |
j | 4 | 15 |
- There are seven jobs that must be processed in two operations: A and B. All seven jobs must go through A and B in that sequence - A first, and the B. a)Find the job sequence by Johnson's rule b) What is the total completion time for all seven jobs
job | Process A (hours) | Process B (hours) |
a | 9 | 6 |
b | 8 | 5 |
c | 7 | 7 |
d | 6 | 3 |
e | 1 | 2 |
f | 2 | 6 |
j | 4 | 7 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started