Finulu 10 19 The activity times are 3,4,2,5,7,2,2, and 3 days for activities A1 through A8, respectively. What is the critical path? A1,A2,A3,A4,A8A1,A2,A3,A6,A7,A8A1,A2,A5,A7,A8
Finulu 10 19 The activity times are 3,4,2,5,7,2,2, and 3 days for activities A1 through A8, respectively. What is the critical path? A1,A2,A3,A4,A8A1,A2,A3,A6,A7,A8A1,A2,A5,A7,A8