Five brothers Companys budget and actual costs per unit are provided below for the most recent period. During this period, 800 units were actually produced.

Five brothers Companys budget and actual costs per unit are provided below for the most recent period. During this period, 800 units were actually produced.

Product Budget Cost

Product Actual Cost

Materials

Metres

Unit Price Per Metre

Budget

6

$5.00

$30.00

Actual

6.2

$4.80

$29.76

Direct labour

Hours

Hourly Rate

Budget

5

$5.00

$25.00

Actual

4.8

$5.50

$26.40

Variable overhead

Hours

Hourly Rate

Budget

5

$4.00

$20.00

Actual

4.9

$4.10

$20.09

Total unit cost

$75.00

$76.25

Required:

Given the information above, compute the following variances. Also indicate if the variances are favorable or unfavorable.

1. Materials price variance

2. Materials quantity variance

3. Direct labour rate variance

4. Direct labour efficiency variance

5. Variable overhead rate variance

6. Variable overhead efficiency variance

7. Please give some managerial suggestions based on your calculation.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operational Auditing For Management Control

Authors: Edward F Norbeck

1st Edition

0814451853, 978-0814451854

More Books

Students also viewed these Accounting questions

Question

Describe three other types of visual aids.

Answered: 1 week ago