Five data entry operators work of Data Processing department each day for 20 working days the number of defective records in a sample of 250
Five data entry operators work of Data Processing department each day for 20 working days the number of defective records in a sample of 250 records typed by these operators has been noted, as follows: | ||||||||||
SampleNo. | No. Defective | SampleNo. | No. Defective | |||||||
1 | 7 | 11 | 12 | |||||||
2 | 5 | 12 | 5 | |||||||
3 | 10 | 13 | 20 | |||||||
4 | 10 | 14 | 4 | |||||||
5 | 11 | 15 | 11 | |||||||
6 | 8 | 16 | 8 | |||||||
7 | 6 | 17 | 12 | |||||||
8 | 9 | 18 | 4 | |||||||
9 | 6 | 19 | 6 | |||||||
10 | 13 | 20 | 25 | |||||||
a) Establish a three-sigma control chart for monitoring the number of defective records. | ||||||||||
What is the upper limit? | ||||||||||
What is the lower limit? | ||||||||||
b) Based on the chart created in (a), was there any day when the process was not in control? Which days? | ||||||||||
c) What action or corrective action would you suggest to eliminate the out of control event? | ||||||||||
d) The industry standards are 0.10 and 0.01, respectively. What does this imply about Georgia Bank's own standards? |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started