Question
Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of completion is
Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of completion is provided in the following table.
Job | Processing Time (days) | Due Date (days) |
A | 14 | 21 |
B | 7 | 10 |
C | 2 | 3 |
D | 3 | 6 |
E | 9 | 24 |
Using the shortest processing time (SPT) rule, it can be concluded that the average flow time for these five jobs is?
Step by Step Solution
3.28 Rating (145 Votes )
There are 3 Steps involved in it
Step: 1
The shortest processing time SPT rule is a scheduling rule that orders jobs in the ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get StartedRecommended Textbook for
Operations Management
Authors: William J Stevenson, Mehran Hojati, James Cao
6th Canadian Edition
1259270157, 978-1259270154
Students also viewed these General Management questions
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
View Answer in SolutionInn App