Five jobs are waiting to be processed. Their processing times and due dates are given below. You want to schedule the jobs using the critical

Five jobs are waiting to be processed. Their processing times and due dates are given below. You want to schedule the jobs using the critical raio scheduling rule.
Job
Processing Time(days)
Job Due Date(days)
A
12
12
B
8
15
C
15
10
D
18
17
E
22
20
- Assume that all jobs arrived on day 0.
- Today(current day) is day 0.
TIP: if today is day 0 and Job C's processing time is expected to be 15 days, the workdays remaining for job C is 15 days.
Calculate the Critical Ratio(CR) for Job C:
enter your response here (round to two decimal places)
Calculate the Critical Ratio(CR) for Job D:
enter your response here (round to two decimal places)
Between Job C and D, which job should be scheduled earlier using the critical raio scheduling rule?
A.
Job D
B.
Job C

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals of Management

Authors: Robbins, DeCenzo, Coulter

7th Edition

132996855, 0-13-610982-9 , 9780132996853, 978-0-13-61098, 978-0136109822

More Books

Students also viewed these General Management questions