Flapjack Corporation had 7,784 actual direct labor hours at an actual rate of $12.00 per hour. Original production had been budgeted for 1,100 units, but

Flapjack Corporation had 7,784 actual direct labor hours at an actual rate of $12.00 per hour. Original production had been budgeted for 1,100 units, but only 967 units were actually produced. Labor standards were 7.4 hours per completed unit at a standard rate of $13.12 per hour.

The direct labor rate variance is

a.$8,718.08 unfavorable

b.$8,718.08 favorable

c.$7,709.13 unfavorable

d.$7,709.13 favorable

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Global Marketing

Authors: Svend Hollensen

8th Edition

1292251808, 9781292251806

Students also viewed these Accounting questions