Question
1 Approved Answer
Flexible Budgeting and Variance Analysis I Love My Chocolate Company makes dark chocolate and light chocolate. Both products require cocoa and sugar. The following planning
Flexible Budgeting and Variance Analysis
I Love My Chocolate Company makes dark chocolate and light chocolate. Both products require cocoa and sugar. The following planning information has been made available:
Standard Amount per Case
Dark Chocolate Light Chocolate Standard Price per Pound
Cocoa lb lb $
Sugar lb lb
Standard labor time hr hr
Dark Chocolate Light Chocolate
Planned production cases cases
Standard labor rate $ per hr $ per hr
I Love My Chocolate does not expect there to be any beginning or ending inventories of cocoa or sugar. At the end of the budget year, I Love My Chocolate Company had the following actual results:
Dark Chocolate Light Chocolate
Actual production cases
Actual Price per Pound Actual Pounds Purchased and Used
Cocoa $
Sugar
Actual Labor Rate Actual Labor Hours Used
Dark chocolate $ per hr
Light chocolate per hr
Required:
Prepare the following variance analyses for both chocolates and total, based on the actual results and production levels at the end of the budget year:
Direct materials price variance, direct materials quantity variance, and total variance.
Direct labor rate variance, direct labor time variance, and total variance.
Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. If there is no variance, enter a zero.
a Direct materials price variance $fill in the blank
Direct materials quantity variance $fill in the blank
Total direct materials cost variance $fill in the blank
b Direct labor rate variance $fill in the blank
Direct labor time variance $fill in the blank
Total direct labor cost variance $fill in the blank
The variance analyses should be based on the
amounts at
volumes. The budget must flex with the volume changes. If the
volume is different from the planned volume, as it was in this case, then the budget used for performance evaluation should reflect the change in direct materials and direct labor that will be required for the
production. In this way, spending from volume changes can be separated from efficiency and price variances.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started