Question

1 Approved Answer

Flint Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling and finishing.

Flint Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling and finishing. Parts are produced in batch sizes of 30 parts. A part requires 5 minutes in milling and 7 minutes in finishing. The move time between the two operations for a complete batch is 5 minutes.

Under the lean philosophy, the part is produced in a cell that includes both the milling and finishing operations. The operating time is unchanged; however, the batch size is reduced to 4 parts and the move time is eliminated.

Determine the value-added, non-value-added, and total lead times, and the value-added ratio under the traditional and lean manufacturing methods. If required, round percentages to one decimal place.

Traditional Philosophy Lean Manufacturing Philosophy
Value-added time ____ min _________ min
Non-value-added time ____ min _________ min
Total lead time ____ min _________ min
Value-added ratio (as a percent) ____ % _________

%

Please post clearly formatted answer. Coud not follow previous answer from user. Thank You!

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Systems Direct Auditing Practice Case IBM Book Workbook And 5.25 Disk

Authors: Dieter Weiss, Gaylord N. Smith

1st Edition

0538809051, 978-0538809054

More Books

Students also viewed these Accounting questions

Question

d. Who are important leaders and heroes of the group?

Answered: 1 week ago