Fogerty Company makes two productstitanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor-Hours per Unit Annual Production Hubs 0.70 23,000 units Sprockets

Fogerty Company makes two productstitanium Hubs and Sprockets. Data regarding the two products follow:

Direct Labor-Hours per Unit Annual Production
Hubs 0.70 23,000 units
Sprockets 0.30 57,000 units

Additional information about the company follows:

  1. Hubs require $39 in direct materials per unit, and Sprockets require $12.

  2. The direct labor wage rate is $17 per hour.

  3. Hubs require special equipment and are more complex to manufacture than Sprockets.

  4. The ABC system has the following activity cost pools:

Estimated Activity
Activity Cost Pool (Activity Measure) Overhead Cost Hubs Sprockets Total
Machine setups (number of setups) $ 22,770 115 92 207
Special processing (machine-hours) $ 164,000 4,100 0 4,100
General factory (organization-sustaining) $ 323,900 NA NA NA

Required:

1. Compute the activity rate for each activity cost pool.

2. Determine the unit product cost of each product according to the ABC system.

Fogerty Company makes two productstitanium Hubs and Sprockets. Data regarding the two products follow:

Direct Labor-Hours per Unit Annual Production
Hubs 0.70 23,000 units
Sprockets 0.30 57,000 units

Additional information about the company follows:

  1. Hubs require $39 in direct materials per unit, and Sprockets require $12.

  2. The direct labor wage rate is $17 per hour.

  3. Hubs require special equipment and are more complex to manufacture than Sprockets.

  4. The ABC system has the following activity cost pools:

Estimated Activity
Activity Cost Pool (Activity Measure) Overhead Cost Hubs Sprockets Total
Machine setups (number of setups) $ 22,770 115 92 207
Special processing (machine-hours) $ 164,000 4,100 0 4,100
General factory (organization-sustaining) $ 323,900 NA NA NA

Required:

1. Compute the activity rate for each activity cost pool.

2. Determine the unit product cost of each product according to the ABC system.

Fogerty Company makes two productstitanium Hubs and Sprockets. Data regarding the two products follow:

Direct Labor-Hours per Unit Annual Production
Hubs 0.70 23,000 units
Sprockets 0.30 57,000 units

Additional information about the company follows:

  1. Hubs require $39 in direct materials per unit, and Sprockets require $12.

  2. The direct labor wage rate is $17 per hour.

  3. Hubs require special equipment and are more complex to manufacture than Sprockets.

  4. The ABC system has the following activity cost pools:

Estimated Activity
Activity Cost Pool (Activity Measure) Overhead Cost Hubs Sprockets Total
Machine setups (number of setups) $ 22,770 115 92 207
Special processing (machine-hours) $ 164,000 4,100 0 4,100
General factory (organization-sustaining) $ 323,900 NA NA NA

Required:

1. Compute the activity rate for each activity cost pool.

2. Determine the unit product cost of each product according to the ABC system.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Basel III, The Devil And Global Banking

Authors: D. Chorafas

2nd Edition

0230353770, 9780230353770

More Books

Students also viewed these Accounting questions

Question

Total variance = Standard cost- ___________ .

Answered: 1 week ago

Question

=+24. Friday the 13th, accidents. The researchers in Exercise

Answered: 1 week ago