Answered step by step
Verified Expert Solution
Question
1 Approved Answer
following activities with their predecessor activities and activity durations in weeks are given for a project. Draw the network diagram Identify critical path calculate earliest
following activities with their predecessor activities and activity durations in weeks are given for a project.
- Draw the network diagram
- Identify critical path calculate earliest start time and latest finish time.
Activity | A | B | C | D | E | F | G | H |
predecessor | - | A | A | A | B | D | C,E | F,G |
time | 3 | 4 | 5 | 4 | 2 | 9 | 6 | 2 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started