Following are simplified job cost sheets for three custom Jobs at the end of June for Custom Patios Job Number 102 Materials $ 24,000 Labor 11,000 Overhead 4,340 Job Number 103 Materials $ 50,00 Labor 29,700 Overhead 13,068 Job Number 104 Materials $ 57.000 Labor 38,00 Overhead 16,720 All jobs were started in June Overhead is applied with a predetermined rate based on direct labor cost. Jobs 102 and 103 were finished in June, and Job 104 will be finished in July 1. What was the total cost of direct materials requisitioned in June? 2. How much total direct labor cost was incurred in June? 3. How much total cost is transferred to Finished Goods Inventory in June? Complete this question by entering your answers in the tabs below. Reg 1 and Reg 3 1. What was the total cost of direct materials requisitioned in June? 2. How much total direct labor cost was incurred in June? Direct Materials Complete this question by entering your answers in the tabs below. Req 1 and 2 Req3 1. What was the total cost of direct materials requisitioned in June? 2. How much total direct labor cost was incurred in June? Direct Materials Job June 102 103 104 Total Direct Labor June Job 102 103 104 Total Ron Req3 > Overhead 16,720 All jobs were started in June. Overhead is applied with a predetermined rate based on direct labor cost Jobs 102 and 103 were finished in June, and Job 104 will be finished in July 1. What was the total cost of direct materials requisitioned in June? 2. How much total direct labor cost was incurred in June? 3. How much total cost is transferred to Finished Goods Inventory in June? Complete this question by entering your answers in the tabs below. Roq 1 and 2 Reg 3 How much total cost is transferred to Finished Goods Inventory in June? Job Direct Materials Applied Overhead Total Cost Cost Transferred to Finished Goods Direct Labor $ 11 000 102 103 29.700 38.000 104 Total $ 78,700