Following is the summary of suggestions made: Network Design could be reduced from 1 0 days to 8 days at an additional cost of $

Following is the summary of suggestions made:
Network Design could be reduced from 10 days to 8 days at an additional cost of
$4,000. This task was already underway, but they can still do this, if they make the
change immediately.
The ordering/receiving of the new ventilation system can be reduced to 12 days by
using a different shipping method, estimated to cost an additional $6,000.
The contractor can pay his crew extra to work overtime and reduce the installation
time of the ventilation system down to 4 days at an additional cost of $3,000.
The ordering/delivery time for racks can be reduced by half if a different shipment
method is used. The expediting of the shipping requires an additional $3,500.
Rack installation time had many suggestions:
a. Installation time can be reduced to 14 days if the contractor is allowed to hire
temporary additional crew members, estimated to cost an additional $3,850.
b. Allow the regular crew to work overtime and finish the installation in 12 days,
estimated to cost an additional $5,000.
c. Of course, they can do both, and that would reduce the installation time down
to 6 days, estimated to cost an additional $8,000.
The installation of power supplies and cables can begin once some racks have been
installed. This approach would allow the team to complete the power and cable
installation within 1 additional day once all racks have been installed.
Now the objective was to find the most cost-effective way to finish the project by mid-
December (15th). The team started their analysis by working on the latest plan, which was
based on the 7-day working week.
Based on the additional information, use the ProjectLibre file provided to create a project plan
that ends at the latest by mid-December, and answer the following questions:
Question 1: Using project crash principles
Since John must show the changes to get approval, list all that your team suggests in the order
by which they were changed in the original plan. Since it is not known what additional budget
Jill would approve, make sure to compress the schedule starting with the least costly option
and its implications (what is the new project ending time and the cost). Continue the process
until you can reach the desired deadline or no more crashing is possible.
What is the least costly option that you would recommend? How much additional
funding is needed, and what would be the new end date?
If you have not reached the desired end date, what is the next least costly option that
you would recommend? How much additional funding is needed, and what would be
the new end date? Please repeat this process until you have reached the desired end
date, or you run out of options for compressing the schedule.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management

Authors: Patrick J. Montana, Bruce H. Charnov

5th Edition

1438004826, 978-1438004822

More Books

Students also viewed these General Management questions

Question

2. Discuss the evidence for psychopathy as a heritable disorder.

Answered: 1 week ago

Question

How does your language affect the way you think?

Answered: 1 week ago