Following list of activities is finalized by project manager for a small Production line maintenance project. Activity Preceding Activity Activity Duration (days) A None 2
Following list of activities is finalized by project manager for a small Production line maintenance project.
Activity | Preceding Activity | Activity Duration (days) |
A | None | 2 |
B | None | 5 |
C | A | 10 |
D | B | 3 |
E | C | 4 |
F | C | 5 |
G | D | 2 |
H | E, F, G | 1 |
- How many days the project will take to complete? (You do not need to show the network diagram here) [1 mark]
- Identify the critical path (You do not need to show the network diagram here, just name the critical activities) [1 mark]
- How critical path analysis helps project manager in managing time and cost?[2 marks]
- Assume the Total Slack of activity E is 4 days. What does this Total Slack mean [2 marks]?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started