Question

1 Approved Answer

For a certain project, the net present value at a discount rate of 15% is OMR 30,600, and at a rate of 18% the net

For a certain project, the net present value at a discount rate of 15% is OMR 30,600, and at a rate of 18% the net present value is OMR - 10,300. What is the internal rate of return of the project?

a) 16.6%

b)16.5%

c) 15.7%

d) 17.2%

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

IT Audit In China

Authors: LIU Ruzhuo

1st Edition

981428145X, 978-9814281454

More Books

Students also viewed these Accounting questions